1、潮莞高速連接大道新建工程預(yù)制箱梁架設(shè)施工方案1目錄第一章編制說明.................................................................................................................................31.1編制依據(jù)...................................................
2、...............................................................................31.2編制目的.................................................................................................................................31.3
3、適用范圍.................................................................................................................................3第二章工程概況...............................................................................
4、..................................................32.1工程簡介..................................................................................................................................32.2設(shè)計概況........................
5、..........................................................................................................42.3計劃工期..........................................................................................................
6、........................42.4主要技術(shù)標(biāo)準..........................................................................................................................42.5自然條件........................................................
7、..........................................................................42.6施工條件..................................................................................................................................62.7主要工程
8、數(shù)量..........................................................................................................................7第三章工程重難點分析.....................................................................................
9、................................73.1建設(shè)標(biāo)準高、工期緊.............................................................................................................73.2安全和環(huán)境要求高......................................................
10、...........................................................73.3運梁距離長、沿途山區(qū)地形復(fù)雜、運輸條件差..................................................................8第四章總體目標(biāo)...............................................................
11、..................................................................84.1工期目標(biāo)..................................................................................................................................84.2質(zhì)量目標(biāo)........
12、.........................................................................................................................84.3安全目標(biāo)...........................................................................................
13、......................................84.4環(huán)境保護、水土保持目標(biāo)......................................................................................................84.5文明施工目標(biāo).......................................................
14、..................................................................94.6職業(yè)健康管理目標(biāo).................................................................................................................94.7總體施工組織布置.................
15、.................................................................................................94.7.1施工組織管理機構(gòu).......................................................................................................94.7.2
16、施工隊伍部署及任務(wù)劃分..........................................................................................9第五章主要大型臨時設(shè)施...........................................................................................................
17、....105.1布置原則................................................................................................................................105.2架橋機拼裝場地及運梁便道..............................................................
18、..................................105.2.1拼裝場地施工.............................................................................................................105.3施工準備.......................................................
19、.........................................................................115.3.1技術(shù)準備.....................................................................................................................115.3.2臨時工程........
20、.............................................................................................................115.3.3機具設(shè)備及材料.................................................................................................
21、........115.3.4施工隊伍調(diào)遣............................................................................................................125.3.5其它..................................................................................
22、..........................................12第六章施工進度計劃.......................................................................................................................126.1主要作業(yè)指標(biāo).....................................
23、..................................................................................126.2施工順序、進度安排...........................................................................................................136.2.1施工順序......
24、..............................................................................................................136.3工期保證措施...................................................................................................
25、....................136.3.1工期組織保證體系....................................................................................................136.3.2保證工期的組織措施.....................................................................
26、...........................136.3.3保證工期的技術(shù)措施................................................................................................15第七章箱梁、橋墩交接及復(fù)測..................................................................
27、.....................................157.1箱梁的外形尺寸及外觀質(zhì)量的檢查....................................................................................167.2墩臺復(fù)測......................................................................
28、..........................................................16潮莞高速連接大道新建工程預(yù)制箱梁架設(shè)施工方案3第一章第一章編制說明編制說明1.11.1編制依據(jù)編制依據(jù)1、《潮莞高速連接大道新建工程(K0000~K5674.097)施工圖設(shè)計》;2、《公路橋涵施工技術(shù)規(guī)范》(JTGTF502011);3、《公路工程質(zhì)量檢驗評定標(biāo)準》(JTGF8012004);4、《公路工程施工安全技
29、術(shù)規(guī)范》(JTJ07695);5、《公路鋼筋混凝土及預(yù)應(yīng)力橋涵設(shè)計規(guī)范》JTGD622004;6、《起重機設(shè)計規(guī)范》(GBT38112008);7、《架橋機安全規(guī)程》(GB264692011);8、對工程所在地的現(xiàn)場調(diào)查資料;9、我公司擁有的技術(shù)成果、工法成果、機械狀況、施工技術(shù)水平與管理水平以及多年來在類似工程施工實踐中積累的成功經(jīng)驗。1.21.2編制目的編制目的1、合理、科學(xué)、可靠組織施工和部署,明確施工方法和施工工藝。2、明確質(zhì)量
30、目標(biāo),健全保證體系,完善保證措施,確保質(zhì)量滿足設(shè)計及規(guī)范要求。3、明確安全目標(biāo),采取安全可靠措施,確保施工安全、人員和設(shè)備安全。4、明確工期目標(biāo),合理安排生產(chǎn)計劃,保證工期措施得力,確保工程工期滿足業(yè)主要求。1.31.3適用范圍適用范圍本方案適用于潮莞高速連接大道橋涵工程預(yù)制箱梁運輸及架設(shè)工程。第二章第二章工程概況工程概況2.12.1工程簡介工程簡介潮莞高速連接大道新建工程位于廣東省東南部,汕尾市西部,隸屬深汕合作區(qū)管委會,線路總長度為
溫馨提示
- 1. 本站所有資源如無特殊說明,都需要本地電腦安裝OFFICE2007和PDF閱讀器。圖紙軟件為CAD,CAXA,PROE,UG,SolidWorks等.壓縮文件請下載最新的WinRAR軟件解壓。
- 2. 本站的文檔不包含任何第三方提供的附件圖紙等,如果需要附件,請聯(lián)系上傳者。文件的所有權(quán)益歸上傳用戶所有。
- 3. 本站RAR壓縮包中若帶圖紙,網(wǎng)頁內(nèi)容里面會有圖紙預(yù)覽,若沒有圖紙預(yù)覽就沒有圖紙。
- 4. 未經(jīng)權(quán)益所有人同意不得將文件中的內(nèi)容挪作商業(yè)或盈利用途。
- 5. 眾賞文庫僅提供信息存儲空間,僅對用戶上傳內(nèi)容的表現(xiàn)方式做保護處理,對用戶上傳分享的文檔內(nèi)容本身不做任何修改或編輯,并不能對任何下載內(nèi)容負責(zé)。
- 6. 下載文件中如有侵權(quán)或不適當(dāng)內(nèi)容,請與我們聯(lián)系,我們立即糾正。
- 7. 本站不保證下載資源的準確性、安全性和完整性, 同時也不承擔(dān)用戶因使用這些下載資源對自己和他人造成任何形式的傷害或損失。
最新文檔
- 箱梁架設(shè)施工方案
- t梁預(yù)制、架設(shè)施工方案 (1)
- t梁預(yù)制、架設(shè)施工方案 (1)
- 預(yù)制箱梁架設(shè)工程冬季施工方案
- 預(yù)制箱梁架設(shè)工程冬季施工方案
- 箱梁預(yù)制場建設(shè)施工方案
- 25米箱梁架設(shè)施工方案
- 預(yù)制箱梁吊裝架設(shè)施工專項安全方案
- 40m箱梁架設(shè)施工方案
- 箱梁預(yù)制施工方案
- t標(biāo)預(yù)制梁架設(shè)施工方案培訓(xùn)資料
- t梁架設(shè)施工方案
- 預(yù)制箱梁冬季施工方案
- 預(yù)制箱梁安裝施工方案
- 預(yù)制箱梁架設(shè)技術(shù)方案
- 跨鐵路線鋼箱梁架設(shè)施工方案
- 預(yù)制梁場建設(shè)施工方案
- 箱梁架設(shè)施工專項方案
- 25米預(yù)制箱梁施工方案
- 30m預(yù)制箱梁架設(shè)現(xiàn)場施工方法
評論
0/150
提交評論